Here is a selection of my Carpentry since starting my Level 2 Diploma at SGS College, from the end of Feb.to Dec. 2012
The final practical test. 18 hours long, but not all at once!
Completed test! |
Door hung |
Architrave and barge board in place |
Frame leveled and fix to the wall, and the cladding attached |
Stud work complete ready to lift into place to level |
Initial stages the main frame is braced and working out the correct positions for the noggins |
Boxing in a soil pipe
Frame built around the soil pipe |
Then boxed in using plywood, cut around the pipe with a coping saw in two halves |
Repair to moulding
Finished repaired |
Much of the shape carved to match profile |
New section of wood, with pencil marks of what I need to carved away |
Moulding with damaged section cut away |
Loft Hatch and Water Tank
Loft hatch and water tank side view |
Water Tank on platform built up in a pyramid shape to distribute the weight of the tank. |
From below |
Roof Trusses
Barge board and Fascia |
Compound mitre cut on the barge board and 45 degree mitre on the Fascia. |
Barge board cut and attached to the ladders |
I had to extend each truss so that I would be able cut everything to the same length and then attach the Fascia. I used the blue chalked string to mark it on before cutting them to length. |
Ladders built and attached to the end truss to from the verges. (You can just see Andy in this photo who I have been working with.) My ladder is on the far side. |
Noggin cut and attached to the double trusses before fitting the Vellux window |
Diagional braces at 45 degrees, (or less) |
All the trusses plumb and braced. Each brace was marked against each other before securing to the trusses to ensure they were kept at 400 mm centres |
Both end trusses with temporary braces, the other truss plates are at 400 mm centres |
Stairs
The handrail, balustrade and stairs finished, from the side |
The finished stairs and balustrade |
Fitting the last balustrade and the spacers either side |
The hand rail and capping in place, the last balustrade about to go in |
Chris, Ade and Brett hard at work? |
The assembled, wedge and glued stairs, (laid on their wall string side) |
First 3 assembled steps and newel post |
Centre steps wedged and glued then riser screwed to the back of the step |
Dry run of 4 steps and 3 risers, from back |
From front, laid on the outer string |
Dry assembly of two lower steps and risers |
from front |
Newel routed for the lower step and riser |
String fitted to Newel |
String tenon and mortise in Newel |
Newel post with housing for string mortise |
Mortise, cut with a mortiser |
The jig for the stair strings, set up to make the first cut |
Door frame with Scarfe repairs.
Scarfe glued in place & planed back |
Scarfe cut and fitted |
Old hinge repair removed, cleaned up & scarfe cut to fit. |
This repair was planed with the rebate plane to get up against the rebate edge |
Joist Flooring, hung on joist hangers
Joists nailed in place, to the joist hanger |
Chris inserting the joists into the joist hangers |
Pole plate level and screwed to the wall |
Small return section of joist hangers on the pole plate |
Upright secured in place, and the double pole plate is laid at the bottom of the corner |
Cleared Unit |
Removing the old flooring and joists |
Some of the removed kitchen units |
Before I started |
Kitchen Worktops (I worked with Chris Townsend on this)
Worktop in place. (We cut them over long, because they will be re-cut by future students). |
Two tops brought together and secured with dog bone fixings, on the underside. |
The two halves lined up before joining |
(close up) Dog bone cut with router using the jig |
Jig set up |
Worktop before setting up the jig and routing 2nd half |
First edge cut |
Chris ready to start routing out the first cut on our worktop |
Wall units
All the units fitted |
The large wall cabinet I hung on the wall brackets but the smaller the attached fittings were broken so I used a split batten instead. |
Base units
Plinth cut and scribed to fit under the the units, then attached to the unit legs. Doors added, due to the limited number of fittings, I only did a few. |
More base units checking the levels as I progressed and then securing to the walls. |
Base units attached to corner post |
First checked the floor, marked level on wall then introduced the base cabinets. Ensured that each unit was level. |
2nd Fix
Skirting
Lock, handle and catch plate fitted to the door lining |
Architrave
Architrave & door stop attached |
Door & lining
Door hung, hinges cut into the door the lining. 2mm tolerance between door & frame |
Door lining braced to hold square. Held square to the stud frame with wedges |
Stud walls
Assembling stud on the floor the upright centres at every 400mm |
Stud wall assembled and errect. |